2007 – A 400 tonne tower crane is installed on site to allow steel work
to begin. | | Progress Work
began on G1 Glasgow in the summer of 2006, demolishing the internal structure
of the building, and retaining the front A listed Victorian facade.
Principal contactor McLaughlin
& Harvey moved on site in April 2007 to begin construction. This section
provides information and images showing the current progress of the development,
which is scheduled to be ready for occupation in September 2009.
For the latest news on G1 Glasgow, click here. |  |
G1’s Development
Milestones Nov ‘05 - building purchased from
G1 Group March ‘06 - planning request submitted to
Glasgow City Council June ’06 - planning permission
granted June ’06 - demolition begins March
’07 - demolition is completed April ’07
- construction begins January ’08 - steelwork commences
January ’09 - G1 Glasgow Tops Out
| |